Comparing Frame Fatigue Test Results Across Labs: A Fixture and Data Checklist
When two reports disagree, compare the method, specimen, fixture, measured input and endpoint before assigning a cause. Use this checklist to collect the records that make a technical review possible.

If one lab reports a frame failure and another reports completion, compare what each lab tested, what load reached the specimen, and what counted as failure. Matching load settings and cycle targets alone do not show that the two tests were equivalent or that either lab made an error.
Use the checklist below to compare bicycle, scooter or motorcycle frame programmes. The relevant method and specimen boundaries remain specific to each product. A vertical frame load, a steering-column test and complete-vehicle roller running must not be treated as equivalent evaluations.
1. Establish whether the results are comparable
Start with the full method reference, edition, specimen category and programme revision. If one laboratory followed a customer development procedure and the other followed a different standard method, the results may answer different questions. The standard number alone does not define the entire test.
Check the units and meaning of every quoted value. Peak load, load amplitude, load range and mean load are different descriptions. Similarly, a count of actuator commands may not be the same as a count of valid specimen loading cycles. Agree the definitions before comparing numbers.
| Item | Record for Lab A and Lab B | Why it matters |
|---|---|---|
| Method | Reference, edition, clause/internal identifier and deviations | Similar test names can describe different procedures |
| Specimen | Design revision, batch, preparation and assembly | The samples may not represent the same population or condition |
| Setup | Fixture drawing, supports, load point and permitted movement | The boundary conditions determine the load path |
| Input | Actual load history, control mode, frequency and interruptions | Controller settings alone do not establish delivered loading |
| Measurement | Channels, locations, working ranges, verification and acquisition settings | Different measurement paths can show different responses |
| Endpoint | Damage definition, inspection timing, stop code and restart rule | A completed programme and a failure are not interchangeable observations |
2. Check specimen and assembly differences
Nominally identical frames can differ in material condition, manufacturing history, geometry or previous loading. Trace the design revision and batch, then document any conditioning, earlier test, transport damage, repair or rework. Avoid drawing a population-level conclusion from one specimen on each machine.
Record installed parts and assembly state. For a bicycle frame, the selected supports and loading interface belong to the approved method. For a scooter assembly, steering-column extension, locking condition and attached components may be relevant. For a motorcycle frame, installed masses and mounting interfaces can be part of the defined boundary. These are examples of information to check, not universal setup instructions.
Do not reuse a previously fatigued specimen as if it were a fresh matched sample. If a reference artifact or non-destructive check specimen is used to compare measurement systems, state its purpose and limitations separately from product-life testing.
3. Compare the fixture and load path
Ask for dimensioned setup drawings and photographs showing the supports, actuator connection and loading point. A similar-looking clamp is not proof of the same constraint. Check where rotation or translation is permitted, where contact is intended and how clearances change during the programme.
A change in the distance between a force application point and a support can change the bending moment. Misalignment can introduce an unintended load component. A fixture can also constrain a region that is intended to move. Evaluate these possibilities against the selected method rather than assuming that making the setup more rigid always makes it more correct.
Look for movement at reference marks, changes at fasteners, contact witness marks and damage near the fixture. Distinguish specimen cracking from adapter slip or connection loosening. Changes to fixtures or grips can affect alignment, so the post-change check should reflect the installed arrangement.
4. Review actual loading, not only the setpoint
Compare the control mode and the measured input history over the relevant part of the run. Force control and displacement control can lead to different input histories as specimen stiffness changes. The chosen mode must follow the programme; switching modes merely to match another result does not establish equivalence.
Review frequency, waveform, mean condition, amplitude, ramps and dwell periods. Check whether the required operating points were actually maintained with the specimen installed. A machine reaching a setting without a specimen does not demonstrate loaded performance. Ask what the recorded channel measures and where it is located in the load path.
Do not increase frequency or load to shorten a test without method authorization and a technical review. Dynamic behaviour, temperature and the failure mechanism can change. A shorter run is useful only if it still answers the intended question.
5. Trace the installed measurement chain
List the transducer, adapter, conditioning electronics, controller scaling and software calculation behind each reported value. Check units, sign, range, zeroing and reference status. Compare the working points used for verification with the points used in the programme.
Static calibration and performance under dynamic loading are not identical checks. Determine what dynamic verification is appropriate for the method and installed configuration. The machine, fixtures, specimen and operating condition may affect that assessment; a certificate for a detached sensor cannot answer every question about the running system.
Compare acquisition and recording settings as well. Sampling rate, filtering and saved-data intervals are different items. A slow saved trend can miss a short event, while a filtered channel can show a different peak from a less-filtered channel. Retain the settings with the trace. A difference between two plots is a reason to inspect their data paths, not immediate proof of a defective product.
6. Separate failure, completion and invalid stopping
Establish what each report calls a failure: a defined crack, fracture, change in response, loss of function or another approved condition. Record when inspections took place and whether the time or cycle of first damage is known. If damage is found only at an inspection, its onset may lie between inspections rather than exactly at the last counter value.
A specimen that reaches a planned cutoff without the defined failure is a completion or runout under those conditions. Its eventual failure life has not been measured. Do not enter that cutoff as an exact failure life in a simple average alongside failed specimens. Reliability analysis must account for the observation type and the applicable assumptions.
| Recorded event | What it establishes | What it does not establish |
|---|---|---|
| Defined failure detected | Failure evidence and its recorded time/cycle or inspection interval | The root cause without investigation |
| Programme cutoff reached | No defined failure observed through the stated programme, subject to inspection | Exact failure life or unlimited durability |
| Fixture, alarm or utility stop | A station event requiring review | Automatic specimen failure or automatic valid completion |
Keep pause, power-loss, restart and retest records. Define whether cycles outside tolerance count and how the programme handles recovery. An alarm may be useful evidence, but it does not replace specimen inspection or an approved decision about result validity.
Use one comparison record for both laboratories
For each item in the comparison checklist, record Lab A evidence / Lab B evidence / difference or missing record / agreed next check / responsible person. Link each entry to the original file or setup photograph. A matching nominal setting is not a substitute for evidence of the delivered input.
Classify the conclusion as not yet comparable, comparable with stated limitations, or ready for a controlled follow-up, and state why. These are investigation planning labels, not pass/fail criteria or proof that either laboratory is at fault. Keep the original reports unchanged and issue any clarification through the responsible laboratory’s process.
7. Investigate in an order that preserves evidence
- Preserve the original record. Save raw files, settings, setup photographs and the damaged specimen or agreed evidence before adjusting the machine.
- Build the two-laboratory comparison. Mark differences and missing information rather than filling gaps with assumptions.
- Check obvious non-equivalence. Resolve method, specimen state, load definition and endpoint differences before commissioning another full fatigue run.
- Verify suspected setup or measurement issues. Use the approved references, suitable artifacts or representative fresh specimens as appropriate. Do not repeatedly load a damaged part to prove the original result.
- Plan a controlled follow-up. Agree sample allocation, factors held constant, factors changed and evidence needed. Avoid changing the fixture, programme and specimen batch together if the purpose is to isolate one cause.
- Close the investigation with its limits. State what was established, what changed and what remains unproven. Do not replace all material/manufacturing variation with a machine explanation.
Same-laboratory repeatability and cross-laboratory reproducibility describe different comparison conditions. A stable repeated check can support confidence in one setup, but it does not alone prove equivalence between laboratories or establish product-life statistics.
Records to prepare before a fixture or equipment review
- Method reference and revision, including approved deviations.
- Specimen drawing, design revision, batch and assembly/preparation history.
- Fixture drawing, loading dimensions, fastening references and installation photographs.
- Control programme, units and channel/measurement locations.
- Relevant raw load/response files with sampling, filtering and saved-data settings.
- Calibration or verification scope, working points and relevant equipment changes.
- Inspection evidence, damage location, stop code, interruptions and restart/retest history.
Share only information you are authorized to disclose. Describe a missing record as missing rather than reconstructing it from memory.
Match the next equipment discussion to the actual load path
For a bicycle vertical programme, review the bicycle frame vertical fatigue testing machine and the vertical fatigue setup guide. For a motorcycle structure, use the motorcycle frame vibration test machine as a configuration-review starting point and identify whether the question concerns vibration response or cyclic structural fatigue.
Reviewing a new machine or fixture does not establish the cause of an existing result difference. Confirm the required input, support conditions and measurements before making a purchasing decision. A separate factory acceptance plan can then define how the proposed setup will be demonstrated.
Common result-review questions
Do different results mean one laboratory is wrong?
No. First check whether methods, specimens, setups and endpoints are equivalent. Even a controlled programme can show specimen variation. Establish the evidence before assigning a cause.
Is a valid calibration certificate enough to make results comparable?
No. Review its scope and working range, the installed measurement chain, dynamic conditions, fixtures and method execution as appropriate.
Can a completed cycle target be reported as fatigue life?
It should be identified as completion or runout when no defined failure occurred. The eventual failure life remains unknown; it is not an exact failure observation.
Should the higher cycle result be treated as the better frame?
Not until the loading, specimen population, endpoint and other relevant conditions are comparable. One unpaired result is not a reliable basis for ranking designs.
Review the fixture, input and records together
Send Derui your authorized specimen drawing, method and setup information. If you are specifying new equipment, use the comparison checklist to define the fixture, measurement and acceptance evidence required in the proposal.
References and application note
- NIST: Dynamic Force Calibration — background on time-varying force measurements.
- NIST/SEMATECH handbook: Censoring — background on observations that stop before failure or locate it within an interval.
This checklist supports an engineering investigation. It does not prescribe a universal fatigue method, force, frequency, tolerance or failure criterion. Apply the controlled procedure and obtain the responsible technical review before changing the test or making a product acceptance decision.